Construction Update 10.23.17

Posted by Josey McPhail on 10/23/2017 3:00:00 PM

Construction of the RHS activity facility is moving right along! RHS student Tristan Bethea captured these great shots and awesome video on October 20. Here are a few highlights of the current progress:

*The sub-base for the turf is being installed.

*Half of the foundation for the home side concession and locker room area has been completed.

*Construction of the visitor concession and locker room walls is in progress.

*The ticket booth area is being dug out this week.

*Runways for long jump, triple jump and pole vault have been created along with the pad for high jump.

*Preparations for the goal post foundations are also being made.

We are on track to open this facility in the fall of 2018!

DRONE VIDEO LINK: https://youtu.be/HanBjZ28x6k

10.20.17  Oct 20