Construction Update 11.7.17

Posted by Josey McPhail on 11/7/2017

The construction of the activity facility continues to progress at a wonderful pace. Since the last update, the visitor field house exterior block work has been completed and the metal roof trusses hav​e been installed. Installation of the metal roof panels will be next.

 

At the home field house site exterior and interior block walls are being constructed. Also, plumbing for the restrooms and concession area is being installed. Once the plumbing is completed the second half of the slab will be poured.

 

The footing for the ticket booths have been roughed in with conduit being pulled to the location. The dirt work for bleachers on both the home and visitor sides has begun as well. The turf crew has completed all the concrete pours for the track and field events and are putting the final touches on the sub base for the turf. The crew has also installed a goal post. The next steps will be to finalize and test the sub base and then proceed with installation of the turf.

 

Thank you to our student photography team for these great pictures and drone video footage: https://youtu.be/kaGAwg-711U!

Activity Facility 11.7.17 one  Activity Facility 11.7.17 two  Activity Facility Update 11.7.17 three  Activity Facility Progress 11.7.17 four