Despite the cold weather, progress continues to be made on the RHS activity facility!  The concrete pad for the home bleachers has been poured and the bleachers have arrived on site. Installation is underway! An exciting element that was recently added is the installation of the scoreboard, which is nearing completion. The video board and the back logo have been placed on the scoreboard structure. We’re so excited about the interactive abilities this feature will provide. The masonry work is almost complete on the ticket booth and facility entrance. In addition, things are really moving forward with the drywall and painting inside the structures. The project is on time and on budget. We are looking forward to opening this facility this fall! #repmoproud

 

To see the latest drone footage of the facility, captured by Tristan Bethea, visit https://youtu.be/zcnf-Ldzd2w.

 