October 25, 2021 Update

Posted by Josey McPhail on 10/25/2021

Our construction projects are coming along nicely! #RepMOProud

 

The new EC building is about 30% complete, which is right on schedule. The exterior of the high wind shelter is nearly complete. Interior walls are going in, all slab pours have been completed, the storm sewer has been installed along with the water line. Roofing and electric are a few of the next steps.

 

The Schofield gym/high wind shelter is about 40% complete, also right on schedule. The precast panels are set, the underground rough in is complete and the main concrete slab floor has been poured. Next steps include interior masonry walls, framing of corridor walls, roofing and electrical rough-in.