December 15, 2021 Update

Posted by Josey McPhail on 12/15/2021

Construction of the new Early Childhood Center and Schofield gym/high wind shelter projects is moving along as scheduled and on budget!

Progress at the Early Childhood Center includes framing on the exterior of the building, electrical rough in, completed steel installation, started roofing, completed block masonry, started brickwork and air barrier installation. Next steps include completing brickwork and the exterior.

During the past month crews at Schofield have completed all masonry work and metal stud framing, started drywall work, set rooftop HVAC units and completed the roof. Next steps include starting up the HVAC units, complete the metal portion of the roof, paint, lighting, basketball goal installation, acoustical ceiling in the restrooms and setting plumbing fixtures. The gym floor is scheduled to be delivered by the end of the month! #RepMOProud