February 23, 2022 Update

Posted by Josey McPhail on 2/23/2022

Our construction projects are running on time, on budget and will be done before we know it!

The Schofield gym/high wind shelter is about ¾ complete. Over the last month crews installed bathroom elements, gym flooring and bleachers. Next up is finishing the gym floor, installing fencing on the exterior along with preparing for grass. The gym/high wind shelter is expected to be ready for use in mid-March! Details about opening events will be shared soon.

The new Early Childhood Center is also progressing! Exterior brick work has begun along with the roofing. Inside framing has been started along with insulation, ductwork and electrical rough in installations. We look forward to the exterior brick work being completed along with drywall and window installation in the coming weeks. After that, paint! We can’t wait to open this building next school year! #RepMOProud  